Caisson Foundations for Wind Energy Applications
Prof. Guy Houlsby and Byron
Byrne
Suction Caissons are a novel foundation that might be used in a variety
of applications. For example the developing offshore wind industry has
expressed considerable interest in using this design for offshore wind
turbines and anemometer masts. This case presents an interesting problem,
as there are very high moment and horizontal loads, but low vertical
loads, a very different pattern to that experienced by oil and gas structures.
The wind and wave directions may not be co-incident, so the base shear
and moment are not in the same direction. Considerable uncertainty therefore
surrounds how the foundations may perform. An external group (Offshore
Data Ltd) has been considering the viability of using these foundation
types. Several field scale tests have been undertaken to prove various
aspects of performance. Some of the work was sponsored by EPSRC (£16
500) and the Rhodes Trust (B.W. Byrne) and is in collaboration with Offshore
Data Ltd (A joint venture which comprises of EDRO Limited, Mustang Marine
(Wales) Limted and Solar Wheel).
 |
First Trial at Tenby Harbour, South Wales - August
1998
An
initial trial was staged from the Quay at Tenby Harbour. The trial
was used to assess the ease of installation of a suction caisson.
Once installed the caisson was subjected to fast and slow tensile
loading tests to assess theoretical calculations of capacity. The
photo on the left shows the caisson being prepared for installation,
with Prof. Guy Houlsby standing in front for scale. Workers on
top of the caisson are attaching hoses through which the suction
was applied during the installation. The photo on the right shows
the caisson being lowered steadily into the water by a crane. Once
a firm seal with the sea-floor was made suction was applied and
the caisson embedded itself. The crane used for lowering the caisson
in to the water was also used to apply the tensile loading. Once
the loading tests were completed the caisson was removed using
overpressure and installed in a different location to further the
understanding of the installation process.
|
  |
Second Trial at Burry Port, South Wales - September
1998
A second trial was held at Burry Port to assess
the moment capacity of the caisson. The photo on the left shows
the set-up of the caisson and loading frame at low tide before
the caisson was installed. The photo on the right shows the layout
during the loading test. A horizontal load was applied at some
distance above the top of the caisson - applying a moment to the
caisson. Rotation, pore pressure and horizontal load were recorded
during the test, which enabled an assessment of the rotational
capacity of the caisson. Once the test was completed the caisson
was removed using overpressure. |